Financing Long-term Hydropower Requires Mitigating Risks Prior To ROI The long-term, relatively steady amount of money generated from producing power at hydroelectric facilities is alluring to investors, but developers must provide investors clear pathways from conception to return on investment.
By Andrew Landry
Hydropower is a mature technology, but opportunities exist to develop
new facilities or expand the output of existing plants. Hydro projects
are attractive in that they have low operating costs, do not emit
greenhouse gases and offer extremely long service lives. At the same
time, they require significant early capital expenditures and have
potential long regulatory approval processes.
Investors will commit funds toward the development of an energy
project in general based upon the project's risks and expectations of
future revenue streams. Therefore, to access capital, project developers
must identify the revenue streams that will be used to service the debt
and provide a return on investment to the equity investors.
Developers
must also have a plan to minimize regulatory and construction risks. This article explains why developers must identify what revenue
streams exist regardless of whether the project developer is an
individual or a multi-billion-dollar conglomerate.
Development
Development of an energy project consists of three phases:
pre-development stage; from decision to invest to the start of
construction; and construction phase.
Pre-development
Pre-development begins with an idea, such as the identification of a quality site for a new hydroelectric project. This stage also involves accumulating pieces of the project and preparing a well-developed business plan. Typically, this stage is highly risky and any flaw in the project, even a minor one, can kill it. While it is generally useful to minimize the rate at which cash is spent, it is absolutely necessary at this stage to fund as many expenses as possible from existing cash flows.
The pre-development phase will almost certainly include site
identification, high-level engineering (including selection of
technology and construction technique), preliminary review of
environmental concerns, identifying likely revenue streams, and
obtaining the preliminary permit from the Federal Energy Regulatory
Commission.
A well-developed business plan that estimates licensing cost and
timeline, construction cost, operating costs, revenue streams, and pro
forma income will initially be necessary for either internal management
or outside investors. It will be required to support long-term financing
and should evolve based on higher amounts of available information.
This information must be sufficient to justify the substantial
investment required to move forward with licensing and engineering in
the anticipation of construction.
Decision to invest
The decision to invest to the start of construction will include the entire FERC licensing process, as applicable, including conducting the necessary studies identified in a FERC-approved study plan, filing and litigating a license application, obtaining any necessary state and local approvals (e.g. water quality certifications), obtaining ownership or an option to own the project site, conducting detailed engineering, and selecting an engineering, procurement and construction contractor. Due to the potential for significant issues to arise during this phase, funding at this point in development generally must come from equity investors.
Construction phase
Construction commences after the receipt of all regulatory approvals and the execution of an EPC contract. By this point, most risks associated with the project have been eliminated or managed. Given the anticipated revenue stream, a large number of investors, both debt and equity, are likely to be interested at this stage. Some developers will even look to "cash out" at this stage by transferring their project to a larger player.
Construction commences after the receipt of all regulatory approvals and the execution of an EPC contract. By this point, most risks associated with the project have been eliminated or managed. Given the anticipated revenue stream, a large number of investors, both debt and equity, are likely to be interested at this stage. Some developers will even look to "cash out" at this stage by transferring their project to a larger player.
Revenue streams
Similar to other renewable energy sources, hydro projects potentially
have several revenue streams, most notably payments for: energy,
capacity and renewable energy credits or certificates. Regional grid
operators compensate generators for the ability to restart without
outside power since these can be used to restore service following a
blackout (black start service). Some hydro projects are capable of
providing such service. Federal regulations also require downstream
hydro projects to reimburse upstream headwater project owners for an
equitable part of the additional energy production possible at a
downstream hydropower project resulting from the regulation of river
flows by an upstream hydropower project.
Energy payments are the backbone of the revenue streams of most hydro
projects. Typically, banks and other investors will not invest in a new
project unless there is certainty in the power purchase agreement.1
A number of states, including California, Connecticut, and
Massachusetts have enacted long-term contracting programs to support
development of renewable projects, including hydro projects policies
obviously vary from state to state, so it is critical to understand the
program in the state in which your project is located. It is also worth
understanding those programs in neighboring states because they may
accept projects from neighboring states and may offer prices and terms
that are more advantageous than those offered in host states. The
programs frequently include a request for proposals and the requests
have fixed deadlines, so early investigation is key.
A more recent policy development relates to group or community "net
metering." Several states, including New York and New Hampshire, allow
multiple customers receive net metering benefits from a single renewable
energy project, including hydro projects. This policy allows generators
to sell their wholesale energy at retail energy prices without becoming
a licensed competitive energy supplier.
Pursuing legislative or regulatory strategies is an option if your
project does not neatly fit the existing state program. For example, in
2009, Maine tidal and offshore wind developers successfully lobbied for a
change in the law to provide funding for ocean energy via the Maine
Ocean Energy Act. This legislation resulted in a long-term contract for
Ocean Renewable Power Company's (ORPC) hydrokinetic project to be
installed near Eastport, Maine.
Organized and non-organized markets
For projects located in regions that have wholesale markets administered by Regional Transmission Organizations, which FERC refers to as organized markets, another option is to rely on market revenues. Commercial lenders are increasingly willing to accept forecasts of market prices to support project financing. I have represented a major regional bank in financing acquisition of an existing hydroelectric project based on market forecasts and have also seen project upgrades financed in this manner. In most regions, natural gas generators tend to set the market clearing price for energy in most hours, therefore forecast prices are going to track the cost of natural gas generation. Lenders will want a forecast from a reliable source and will err on the low side to be conservative.
For projects not located in organized markets, utilities retain their
obligation to purchase energy from small power production facilities
under the Public Utility Regulatory Policies Act, including hydro
projects of 80 MW or less. However, even in organized markets, hydro
projects under 20 MW are presumed to continue to be eligible for
contracts as qualifying facilities. In particular, in adopting Order No.
688, FERC established a rebuttable presumption that qualifying
facilities with a capacity lower than 20 MW do not have
nondiscriminatory access to markets. Of course, in organized markets,
avoided costs are likely to equal projected market clearing prices, on
which lenders may offer financing in any event.
Payment types
Capacity payments are the second major potential revenue stream. In organized markets, these can be substantial. The most recent forward capacity auction conducted by ISO New England, the clearing price for capacity was $9.55 per kW each month. FERC rules relating to capacity markets have been evolving quickly due to the perceived lack of firmness of many currently qualified resources. In general, it appears that these rules will favor stable projects and that prices are likely to increase.
Renewable energy certificates (REC) are a state-created product
intended to achieve clean energy goals. There is typically a bilateral
market for REC, but many contracts tend to be of short duration,
typically one to three years). It has been my experience that lenders
are wary of relying on these revenues because RECs are a product of
state policy, and state policy is always subject to change.
However, two recently completed hydro projects in Maine were able to
obtain long-term contracts for REC sales. The 2.3-MW Stillwater B
project obtained a REC-only contract for 15 years with a Massachusetts
utility. Its sister, the 3.75-MW Orono B project, obtained a bundled
15-year contract with a Rhode Island utility for energy, capacity and
REC. Their success in obtaining such long term deals likely results from
the anticipation that the renewable policies of these states are stable
and that hydro projects are likely to be reliable
Production tax credits under the Internal Revenue Code have
historically been a desirable revenue stream to investors. However, this
incentive was the subject of periodic review by Congress, and in 2014
the program was not renewed. It is possible that this program could
return or that other programs could emerge such as "hydroelectric
production incentives" previously authorized, but not implemented.
Finally, individual projects could qualify for a variety of grants or
incentives. The U.S. Department of Energy has periodically offered
programs for emerging technologies such as hydrokinetics. The U.S.
Department of Agriculture, through Rural Development and the Rural
Utilities Service, offers incentives for traditional technologies,
generally on a regular basis. States offer a wide variety of economic
development and renewable energy incentives that may be applicable to
energy projects. The Database of State Incentives for Renewables &
Efficiency at www.dsireusa.org is a particularly useful resource for finding current programs that may be applicable to your project.
Eliminating risks
The perception of risk can kill even a promising hydroelectric
project. Developers must work vigorously to identify and manage any and
all risks associated with intended projects. Because the FERC licensing process can be long and expensive, some
strategies are available to reduce risks associated with this process.
First, two types of projects are exempt from licensing: Small hydropower
projects, 10 MW or less, that will be built at an existing dam, or
projects that utilize a natural water feature; and projects on an
existing conduit (e.g. an irrigation canal) up to and less than 40 MW.
In addition, Congress has directed FERC to investigate the
feasibility of a two-year licensing process for projects at non-powered
dams and closed loop pumped storage projects. For existing projects
scheduled to relicense, the process provides a low-cost option to expand
a project. The Stillwater B and Orono B hydro projects, which are now
owned by Brookfield Renewables, were approved as part of a larger scale
relicensing process. Amended licenses for efficiency improvements at
existing projects, such as new turbine runners, can generally be
obtained at moderate expense. For other projects, FERC's integrated
licensing process is generally available and reduces the licensing
burden as compared to the traditional licensing process.
Obviously, most key licensing issues are likely to be environmental
in nature. Therefore, it is vital to determine the fisheries and other
biological species likely to be affected by your proposed hydro project,
as well as the status of ongoing management efforts. Review existing
literature regarding impacts of your technology on these or similar
species.
Public opposition
Communication with local public officials early in the process is critical. It is also useful to begin broader public outreach as soon as the preliminary permit is in hand. Public meetings can be conducted at minimal expense where potential opponents can be identified and developers can begin making good faith efforts to develop positive relationships. Grassroots efforts can cultivate supporters that may otherwise be silent. Active supporters can create positive momentum at public meetings conducted by FERC and state agencies.
If investors are sought at the pre-development stage, be extremely
careful regarding the terms offered. Investors may request a
disproportionate share of the ownership of or control over your project.
Consult with your attorney and a financial advisor to determine whether
a particular proposal represents a fair balance between the value that
you bring to the transaction and the value that the investor brings.
Keep in mind also that you may require additional funding later, so any
transaction must include sufficient flexibility to allow further
investors to participate.
Know what expectations are reasonable. If you do not know, obtain
qualified legal and financial advice. Agreements that promise too much
to early investors can become an albatross that deters second stage
investors from providing funding.
Technology
Investors will prefer a proven technology. If you are proposing novel technology, be prepared to address in detail how and why this new technology will operate as advertised and can be constructed on time and on budget. Understand the electrical interconnection characteristics of your proposed project site, as well as the local review process.
An
engineering firm that is knowledgeable about the local grid should be
able to provide a reasonable assessment at a modest expense. System impact studies can be expensive. Depending on the early
recommendations of a good engineer, this process may be deferrable to
the second stage of project development.
Site control
Obtaining a FERC license will provide the right of eminent domain only if the project developer has made good faith efforts to obtain site control through arm's length negotiations. Further, the process of obtaining site control over state or federal waters (i.e., for a hydrokinetic project) may require additional regulatory steps. Locking down site control, through an option or otherwise, will provide greater assurance of the viability of a given hydropower project.
In general, my best advice is to build a team of experienced
engineers, environmental consultants, contractors, attorneys, and other
professionals that compliment your organization's existing capabilities
and provide prospective investors with confidence. Together with a
well-developed business plan, this team will attract investors to good
hydro projects.
Note
1Weiss, J., and M. Sarro, "The Importance of Long-term Contracting for Facilitating Renewable Energy Project Development," The Brattle Group, Cambridge, Mass., 2013, page 8.
http://www.renewableenergyworld.com/articles/print/hydro/volume-34/issue-6/articles/financing-long-term-hydropower-requires-mitigating-risks-prior-to-roi.html