NEW YORK CITY --
First Solar Inc., the biggest U.S. solar manufacturer, halted panel
deliveries to the world's largest photovoltaic power plant, which it's
building in Arizona, because construction is ahead of schedule and the
company must slow down to meet contractual milestones.
First Solar won’t
ship additional modules until January to the $1.8 billion Agua Caliente
project and won’t install panels currently sitting on the ground at the
site, said Fred Pech, the power plant’s construction manager. The solar farm is scheduled for completion at the end of 2013 and is 85 percent built.
The company, based in Tempe, Arizona, accelerated
construction on Agua Caliente this year to use panels it produced as far
away as Germany and Malaysia amid a global glut. Now it’s diverting
shipments to other projects to prevent inventories from piling up, said
Aaron Chew, an analyst at Maxim Group LLC in New York.
First Solar delivered
panels to the project “because it was more profitable,” Chew said today
in a telephone interview. “They overdid Agua Caliente.” Expanding its
focus on power plants helped make First Solar the only profitable solar company in the Bloomberg Industries Global Large Solar Index in the the second quarter.
The shutdown probably won’t affect First Solar’s
earnings this year, Chew said. “However, it does highlight the extent
to which they’re pulling things forward, with bigger risks in 2013 and
2014.”
The decision to wind down installation for this year
may be “related to contractors and construction crew, perhaps minimum
number of hours,” Chew said.
First Solar shares fell 19 percent to $19.67 at the close in New York.
Last Module
“We installed the last module for block 10 on Monday,”
Pech said in an interview yesterday a the plant, located on 2,400 acres
of desert about 120 miles (193 kilometers) west of Phoenix. There are
two more blocks of panels planned for the site and “we could be done by
the end of this year, but we’re way ahead of schedule.”
Dozens of boxes of unused panels are piled up at the
site, covered in blue tarps to prevent degradation over the next four
months while First Solar waits to resume installation.
The company has shifted panel deliveries to other solar projects,
Ted Meyer, a spokesman, said in an e-mail today. There are about 200
workers at the Agua Caliente site doing work other than installing
panels.
Biggest Plant
With 85 percent of its panels installed, Agua Caliente
has about 247 megawatts of capacity, making it the the world’s largest
operating solar farm. PG&E Corp.’s Pacific Gas & Electric Co. is buying the power under a 25-year agreement.
The power plant was generating 249 megawatts of
electricity yesterday at 11:30 a.m. local time and its output has
reached as much as 251.3 megawatts under ideal sunlight conditions, Pech
said.
The project received a $967 million loan guarantee
from the U.S Energy Department in August 2011 and was expected to create
400 construction jobs and 10 permanent positions, according to the
agency’s website. Damien LaVera, an agency spokesman, said the guarantee
doesn’t include any specific requirements regarding construction or
employment.
The plant is owned by NRG Energy Inc. and MidAmerican
Energy Holdings Co. Lori Neuman, an NRG spokeswoman, and Ann Thelen, a
MidAmerican spokeswoman, didn’t return phone calls today.
Copyright 2012 Bloomberg