New Hampshire, USA --
The ring of fire is a geologic region that extends in a horseshoe
shape from the bottom tip of South America, up along the Pacific coast
through North America, and looping back through Asia and down to New
Zealand.
It's lined with more than 400 volcanoes, and as the Johnny Cash
song goes, it "burns, burns, burns," which also means it's a geothermal
dream zone.
Some areas on the ring have taken advantage of the immense resources;
New Zealand, for example, has developed more than 800 megawatts (MW) of
geothermal capacity that accounts for about 19 percent of its energy
supply, according to the New Zealand Ministry of Economic Development.
But on the other end of the horseshoe in South America, geothermal
energy remains largely untapped, leaving what Pierre Audinet, clean
energy program team leader of the World Bank's Energy Sector Management
Assistance Program (ESMAP), calls an "open frontier."
"South America has an enormous perceived potential. And there is a
nascent desire of many governments to actually get that potential to
become a reality," explained Audinet. "But it is still not completely
straightforward for a variety of reasons."
Barriers to Development
While many countries to the north, such as Mexico, are slowly putting
geothermal projects online, South American regions are lagging behind
for a variety of reasons — some easily recognizeable, some not.
It is widely known that a major barrier to geothermal development, no
matter the location, is the cost of test drilling. This is by far the
most expensive step in the development process, and many projects
struggle to secure financing due to its high risk. Approximately 50
percent of test drilling produces negative results — zero geothermal
activity — so many commercial banks are very unlikely to finance these
projects. Therefore, much of the development in Latin America, and even
countries in eastern Africa where development is blossoming, has been
led by the private sector, according to Audinet.
While governments have already handed over geothermal concessions to
those private developers to move ahead, "it's not as if you have a
million private sectors with deep pockets able to shell out initial
important capital expenditure to do the test drilling," said Audinet.
There are very few developers that are able to take on these costs, so
many are now simply sitting on concessions, bringing the industry to a
stand-still. And in some cases, explained Audient, the cost of test
drilling is even more expensive because the equipment mobilization
costs, such as bringing drilling rigs to those areas, are very high.
"You end up having hefty capital expenditure just to drill a couple
of wells and verify your geothermal source," he said. "It is a tough
world nowadays for financing. There are talks, appetite, desire, and
competent players, but it will take time."
Slowly governments are increasingly realizing that they need to step
in, but so far they haven't been able to figure out how. "It is still
very much in the open," said Audinet. "There are countries where it is
still a blank slate."
In Chile, for example, the government is trying to figure out how to
channel some type of subsidy or support to private developers. It
recently announced a new renewable energy target of 20 percent by 2025
(excluding hydropower), up from the previous 5 percent goal. However
there are legal and budgetary constraints in the way of achieving the
target. Everything is left to the private sector, from generation to
transmission, which makes it difficult for the government to step in,
said Audinet. "They have straightjacketed themselves into private sector
development, which can be very good, but in other ways can be a
limitation when dealing with a massive financial hurdle," he explained.
Unfortunately, there is no "silver bullet" policy for geothermal
development. "We wish you could put in a FIT [feed-in tariff] and
everything would move along, but unfortunately it doesn't work like that
for this technology," said Audinet.
Adding to the financial pressure, there are also some environmental
concerns for geothermal development. Some of the projects that are being
planned, and even some existing plants planned for expansion, are
located in national parks. Other viable areas for development may exist
on lands where there are indigenous people. This creates additional
developmental hurdles and longer lead-times. According to Audinet,
"these constraints could change as regulations evolve, but it is more
work now."
Project Front-runners
In 2012, Alterra Power Corp., a geothermal developer based in Canada,
announced a partnership with Energy Development Corporation (EDC), a
Philippines-based geothermal developer, to pursue six of Alterra's
geothermal concessions in South America. One of which, its Mariposa
project in Chile, is moving along and could be online by 2017.
"This transaction represents a significant step forward for our
geothermal assets in Chile and Peru," said John Carson, Alterra's CEO.
"EDC is a strong partner with deep expertise, and we're pleased to be
making this next step together." Indeed, EDC has significant geothermal
development experience on the other side of the ring of fire, with
several plants online in the Philippines. The Alterra-EDC partnership
will provide the necessary cashflow for test drilling at the Mariposa
site. EDC will contribute $58.3 million for a 70 percent stake in the
project. Alterra has already identified geothermal potential of more
than 300 MW at the site, but further drilling is required to test for
plant permeability.
Enel Green Power Latin America also has its sights set on Chile, and
formed a partnership with Empresa Nacional de Petróleo (ENAP), the
National Petroleum Corporation in Chile, to develop its geothermal
assets. In August, it signed a $100 million loan with Chile's Banco de
Credito e Inversiones to be disbursed before 2014 in order to develop
its renewable energy investments in the area.
Broadening Financial Reach
In early 2013, the World Bank announced
that it would establish a $500 million fund to help develop geothermal
concessions around the world. According to Audinet, the program has
started to allocate money to help identify test-drilling projects, and
is zeroing in on Latin America "more than other regions," he said.
"We are helping to identify a pipeline of test drilling projects and
helping to lobby and call upon all development banks and donors
interested in geothermal to prioritize more money towards test
drilling," said Audinet. "That is where the money needs to go if we want
to unleash that geothermal potential."
Since geothermal projects have long lead times and can take up to a
decade to complete, Audinet doesn't expect many megawatts to come online
in the next few years. However, he does expect a spike in activity.
"All I can say is that you have a gradual positioning of players,
including financial institutions like the World Bank, InterAmerican
Development Bank, and CAF (a Latin American development bank), that are
conversing on ways to approach projects and move forward," explained
Audinet. "These are conversations that started in the past 10 months so
from that I would imagine that some things would eventually emerge."
http://www.renewableenergyworld.com/rea/news/article/2013/10/an-open-frontier-the-untapped-potential-of-south-american-geothermal
No comments:
Post a Comment