WASHINGTON, D.C. --
On Feb. 12, the Federal Energy Regulatory Commission approved a
successive preliminary permit for Turnagain Arm Tidal Energy Corp. for a
tidal energy project in Alaska.
In February 2013, Turnagain Arm Tidal Energy filed an application
proposing to continue to study the feasibility of the Turnagain Arm
Tidal Electric Generation Project. The project would be located on the
Turnagain Arm of Cook Inlet and adjacent lands of the Kenai Peninsula
Borough and the Municipality of Anchorage, Alaska.
The proposed project would consist of: an 8-mile-long tidal fence
situated between Fire Island in the Municipality of Anchorage and Point
Possession in the Kenai Peninsula Borough consisting of 24, 10-MW
low-head, bi-directional horizontal bulb turbines for a total installed
capacity of 240 MW; a 2-mile-long, 1-mile-wide water storage tank
attached to the tidal fence; one control building/substation onshore
near Anchorage and one near Point Possession; an 18-mile-long, 230-kV
submerged transmission line connecting the tidal fence to the
existing Chugach Electric Association substation at Point Woronzof in
Anchorage and a new substation at Point Possession; and a 28-mile-long,
230-kV above-ground transmission line running parallel to an
existing Homer Electric Association transmission line corridor and
extending from Point Possession to the existing HEA Nikiski substation.
The proposed project would have an estimated average annual generation of 1,271,950 megawatt-hours. The company previously held a three-year preliminary permit for this
site that expired Jan. 31, 2013. During the term of the previous permit,
it filed progress reports outlining its progress towards a license
application. It also filed a Notice of Intent (NOI) to file a license
application and a Pre-Application Document (PAD) for the project under
the commission’s Integrated Licensing Process. This demonstrates that
the company was diligently pursuing the requirements of its prior permit
such that issuing a successive permit is reasonable, FERC noted.
The Hydropower Regulatory Efficiency Act of 2013 authorizes the
commission to extend preliminary permit terms for not more than two
additional years if it finds that the permittee has carried out
activities under the permit in good faith and with reasonable diligence.
“Given that the legislation suggests that five years is a sufficient
maximum period to allow a potential applicant to prepare a development
application, it seems appropriate, as a general matter, to limit to two
years any subsequent permits that follow three-year initial permits,” it
added. “Thus, as indicated below, this successive preliminary permit is
granted for a 24-month term.”
http://www.renewableenergyworld.com/rea/news/article/2014/02/ferc-grants-new-permit-for-240-mw-alaska-tidal-energy-project
No comments:
Post a Comment