New Hampshire, USA --
What will be far and away New Hampshire's largest solar energy system
is beginning to take shape in the town of Peterborough. Its story could
inspire other municipalities searching for answers to infrastructure
and energy problems, and it could also help rewrite the state's new
policies on energy and net metering.
In 2000 the town of Peterborough, comfortably nestled against the
Contoocook River against the Pack Monadnock mountain*, started planning
for its new wastewater treatment plant and decommissioning the old one,
both located just off Route 202 a couple of miles outside of town. Part
of that decommissioning plan included desludging, dewatering and filling
in three shallow sewage lagoons. Fast-forwarding to 2007, the town
voted to reduce its carbon footprint by 10 percent by 2010, and pursued
ways to do that from recycled paper to biomass pellet heating systems on
multiple town buildings: the police station, town hall, and the new
wastewater treatment plant.
Through all of those processes, the town kept thinking of what to do
with those several acres of land at the old treatment plant -- turning
those lagoons into a wide, flat expanse with no trees or wetlands. And
they hit upon an idea: build a solar array to help run the new plant's
pumps, aerators, and mechanical devices. "For solar siting, this is as
close to perfect as you're going to get," recalled Rodney Bartlett, the
town's public works director. Conversations started in 2009 with Borrego
Solar about what might work, and in 2012 they submitted a grant
application to the New Hampshire Public Utilities Commission (PUC) for a
decent-sized system (a few hundred kWs) owned by the town to power the
new plant on-site, and also build new wires to help power the middle
school across the street -- and they were denied, partly because they
wanted to fund it entirely with grant money. They also got wind of new
legislation being worked out that would allow for "virtual" net metering
-- with that, they realized, they could restructure their plans to
create a much bigger project to power not only the new treatment plant
but also gain flexibility to apply excess generation to some of the
town's other buildings, structured through a PPA that would help pay
most of the costs instead of relying so heavily on state funding.
In May 2013 the state's PUC sent out its next request-for-proposals
for renewable energy projects, for a pool of grants that had swelled to
around $4 million -- and received 35 applications totaling $21 million,
ranging from biomass to small hydro upgrades and several
commercial-scale solar project proposals. Among them was the
reconfigured Peterborough project, which stood out due to its size
(double the state's current largest solar installation, currently at the
Manchester airport), its example of land reuse, and how it might more
broadly address the town's economic pressures through sharing energy
costs through the virtual net metering angle. The PUC also saw how the
project would go a long way to helping the state achieve not only its
renewable portfolio standards (25 percent by 2025), pointed out Jack
Ruderman, director of the NH PUC's sustainable energy division.
Moreover, it could address a supply shortfall in renewable energy
certificates (REC). "We're trying to get as many [projects] in place as
we can to add to the supply of RECs," he said, "and this will do that in
a significant way."
Peterborough's new wastewater treament plant. In the foreground, what looks like a field is actually
the sewage lagoon that will be drained and filled in, where the new solar array will be built.
the sewage lagoon that will be drained and filled in, where the new solar array will be built.
Thus earlier this month the Peterborough solar project and its
technical owner, Water Street Solar (a unit of Borrego Solar), were
approved by the PUC for a $1.22 million state grant, to cover a big
chunk of the estimated $2.6 million total system cost. The remaining
$1.4 million will be paid through a long-term PPA, under which the town
would pay 8 cents/kWh, compared with around 14 cents/kWh that the
treatment plant and most town buildings currently pay for electricity,
Bartlett said. Total savings over the 20-year contract would
conservatively be $250,000, but might be twice that, Bartlett said.
Having the old and new treatment plants next to each other also keeps
costs down, not just avoiding transmission and distribution costs to
send power to the grid, but no new onsite transmission is needed because
the new state-of-the-art treatment plant can accommodate it.
Construction is expected to begin by this fall and complete it next
spring, well within the state grant's two-year window. There are even
plans to add a training room at the new plant to show off the array and
the meters as they turn (and don't turn) as power is pushed to the new
plant and back to the grid. "It's another touch of reality for what's
going on," Bartlett said.
What to do with that excess power production is a key to this
proposed project. New Hampshire's net metering rules allowed PSNH to pay
wholesale rate for a site's electricity, or it could be banked and used
as power when needed to offset the electricity bill. Those new rules
for "virtual" net metering, approved last summer and enacted this month,
spell out eligibility for what's generated and used on the same meter
with the same owner. The town, PUC, Borrego, and PSNH are now talking to
figure out how this proposed project could be covered. "The reality of
what we want to do is allowed in the statute, in our mind," Bartlett
said.
The PUC is looking ahead too, eager to know how the Peterborough
project will influence the next grant process being prepared for this
spring or early summer. "I wouldn't be surprised" if other towns come up
with their own proposals to replicate what Peterborough is doing,
Ruderman said.
* (Disclaimer: for most of its life RenewableEnergyWorld.com
called Peterborough home, and it still is for many of our staff. We're
biased.)
http://www.renewableenergyworld.com/rea/news/article/2014/01/rewriting-the-solar-energy-rules-in-one-small-town
No comments:
Post a Comment