TOKYO --
Operators of a wind farm in waters off Fukushima prefecture, site of
the March 2011 nuclear disaster, aim to cut the cost of setting up the
floating turbines by half as they push to commercialize the technology.
The pilot project, funded by the government and led by trading
house Marubeni Corp., began operations on Nov. 11 with a
2-megawatt turbine connected to a substation. Both are about 20
kilometers (12 miles) off the coast of Fukushima. The project’s second
phase will see the installation of two more turbines from Mitsubishi
Heavy Industries Ltd. with 7 megawatts capacity each.
“The most important thing for the first phase was to
float the turbine and make it work, rather than the cost,” Tomofumi
Fukuda, a Marubeni official, said earlier this month in Fukushima after a
ceremony to mark the start of operations. “For the second phase, it
will become very important to figure out how to reduce costs to
commercialize the technology.”
The effort off Fukushima is part of a broader push by
Japan to diversify its sources of energy after the nuclear disaster in
2011 and the subsequent idling of the nation’s fleet of
atomic power stations for safety checks. Prime Minister Shinzo Abe’s
Cabinet has set a target of making floating offshore windtechnology
viable by 2018.
Manufacturing and installing the
2-megawatt wind power generation system, which is able to
generatepower for about 1,700 homes, cost slightly more than 2 million
yen ($20,000) per kilowatt, Fukuda said. Operators want to reduce that
to 1 million yen per kilowatt by the second phase when the next two
turbines are installed, he said.
Cost Considerations
Costs would need to drop to 700,000 yen per kilowatt
to 800,000 yen per kilowatt for floating offshorewind farms to be more
commercially viable, according to the Marubeni official.
At that level, they would become competitive with
offshore wind projects that use monopile foundations to fix turbines to
the ocean floor, Justin Wu, Bloomberg New Energy Finance’s head
ofwind analysis, said.
The goal is to eventually cut the cost to 500,000 yen
per kilowatt for a project with a capacity factor, or how often a
generator runs during a certain period of time, of 40 percent, according
to Fukuda. Onshorewind projects typically operate at 250,000 yen per
kilowatt and a capacity factor of 20 percent, he said.
“It cost us more than we’d anticipated to set up the
station,” Keisuke Murakami, an official in charge of the program at the
Ministry of Economy, Trade and Industry, said.
Floating Turbines
Costs for the project escalated partly because of seas
conditions and high waves from a typhoon that prevented workers from
reaching the site. The 2018 target for Japan is “challenging,” BNEF’s Wu said. “The real cost cutting comes from doing a lot of it,” he said.
Regardless of those hurdles, the project’s backers say
Japan has good reason to push the development of floating
offshore wind farms. Floating turbines can operate in deep waters such
as those surrounding Japan’s 35,000 kilometers of coastline, the sixth
longest in the world. Bottom-fixed turbines are more suited for
shallower waters where foundations are installed directly to the seabed.
Japan has 1,383 gigawatts of available
offshore wind energy, compared with 268 gigawatts onshore, according to
estimates by the Ministry of the Environment.
Development of floating offshore technology would
benefit turbine makers such as Mitsubishi Heavy and Hitachi Ltd., as
well as engineering companies such as Nippon Steel & Sumikin
Engineering Co.
Budget Plan
The government has committed 22 billion yen to the
five- year project, surpassing the original budget of 18.8 billion yen.
For the fiscal year starting April 1, the trade ministry is requesting
31 billion yen.
The additional budget, pending approval, would be used
to install the two turbines, said Murakami. The ministry also wants to
try out different types of technologies for turbines, floating
structures and other components to find cheaper alternatives, he said.
The trade ministry has said the Fukushima project may
be extended to 1,000 megawatts. Operators will need to get approval from
local fishermen to commercialize the project. “Fukushima’s image has been tarnished since March 11,”
said Yuichi Manome, a fisherman from Iwaki City. “By doing this
project, the first of its kind in the world, we can show the world a
different Fukushima.” To install more turbines, Japan would need more
construction vessels, Fukuda said. Currently, Japan’s capacity would be
limited to installing five units a year, he said.
Copyright 2013 Bloomberg