As the renewable energy market shifts and evolves each year, industry
experts need to know where the next hot region will be in order to keep
up with the changing tides.
Luckily, global consultancy Ernst & Young
has released its Country Attractiveness Indices each year since 2003,
which gives a numerical ranking to 30 global renewable energy markets by
scoring renewable energy investment strategies and resource
availability. The indices are updated on a quarterly basis and the most recent report can be found here.
Here is the firm’s assessment of India:
Ding ding, round two. As part of its goal to install
10 GW of solar capacity by 2017, after almost two years, India has
officially launched phase two of its flagship National Solar Mission.
In early October, the first round of phase two saw the Government
invite bids for 750 MW of capacity. The national program aims to reduce
the cost of solar power to compete with other forms of grid-supplied
electricity by 2017; the 2 GW of current installed capacity has helped
cut average costs by about 51 percent since the auctioning of licenses
through the National Solar Mission began in 2010.
Plugging the gap. The new auction will see the
Government offer a baseline tariff of INR5.45/kWh for projects with
capacity 10 MW-50 MW. Developers will then submit bids for additional
funds — up to 30 percent of the project cost — in what will effectively
be a reverse auction process. Winners will be those needing the least
funds. This additional support is part of the Government’s new
“viability gap” funding scheme that will offer around INR18.75b
(US$303m) in grants through the tender process. It will stagger
disbursal of the grants, with 50% to be paid upon plant completion and
the remaining in 10% increments to meet various generation targets.
Local content restrictions or just restricting? The
latest auction also calls for 50 percent of the 750 MW on offer to be
met using domestically manufactured solar cells and panels, with
developers permitted to compete in either or both of the open and
domestic content categories. This requirement is not expected to have an
immediate bearing on the current dispute with the US at the World Trade
Organization over domestic content obligations under phase one of the
solar mission, but it has still raised some concerns that the
restrictions could raise costs and compromise quality given the current
lack of a competitive PV manufacturing sector in India.
Record breaking solar. The sector has also been
boosted by plans to build a 4GW solar plant in Rajasthan state, expected
to be the world’s largest and more than doubling India’s current
installed capacity. In context, the country’s biggest PV project to date
is a 150-MW plant in Maharashtra. There are currently no indications of
whether the “Sambhar Ultra -Mega Green Solar Power Project” will be
based on PV or CSP technology, or a mixture of the two. The JV set up to
run the project, comprising five public sector utilities, hopes to ahve
the first 1-GW phase commissioned by the end of 2016.
Raising the bar. Mid-August finally saw Cabinet
approval for the much anticipated reinstatement of the generation-based
incentive for wind projects, the March 2012 expiry of which resulted in a
42 percent plunge in turbine installations. Wind farms built between
2012 and 2017 will receive INR500/MWh (US$8.20), with installations
during the hiatus period qualifying retroactively. The updated scheme
also increases the cap on the total support a project is eligible for by
61 percent to INR10m/MW (US$164,000).
Too little, too late? The wind sector has of course
welcomed the reinstatement, but the changes may not be enough to enable
India to add the 3 GW per year needed to meet its target of 15 GW of
wind capacity in the period 2012 to 2017. India wind farm developer,
Simran Wind Project Pvt., had planned to add as much as 150 MW annually,
but halted this financial year’s expansion, saying government subsidies
arrived too late. An estimated 1.5 GW of capacity was not built as a
result of last year’s expiry.
Crystal ball gazing. A decree passed in July
requiring all wind farms larger than 10 MW to forecast their generation
for the following day every 15 minutes is also anticipated to make it
harder for the sector to play catch-up with finanacial penalties
incurred where actuals deviate by more than 30 percent. The Wind
Independent Power Producers Association has already filed for an
injunction at the Delhi High Court amid claims that the level of
accuracy required is not possible and could result in penalties
amounting to as much as 15 percent of revenue according to the CEO of
Goldman Sachs-backed ReNew Wind Power.
Offshore anticipation. India’s offshore wind sector
is also playing catch-up, with China relaunching its stalled offshore
wind program and Japan already constructing a huge 1-GW offshore
project. But it looks like India is finally ready to eneter the race,
with the government confirming plans to establish a National Offshore
Wind Energy Authority to carry out resource assessments and ultimately
enter into contracts with project developers. A recent study
commissioned by the government confirmed the huge potential of the
country’s 7,500-km coastline, highlighting the waters off Tamil Nadu
State in particular as holding a significant resource. A more
detailed development strategy by this newly appointed offshore wind body
is now eagerly anticipated.
Infrastructure investment steps up. Increased levels
of policy and project activity in recent months signal a strong outlook
for India’s renewables sector. However, insufficient transmission
infrastructure will continue to be a barrier to large-scale deployment,
and present a risk of further nationwide blackouts.
Acknowledged by politicians and investors alike, things are changing.
The Government plans to spend €6.0 billion (US$7.9 billion) on new
transmission lines across seven states over the next five to six years,
with Germany’s KfW development bank contributing €1.0 billion (US$1.3
billion) in loans and grants toward these so-called “green corridors”.
The first US$400 million tranche of this KfW contribution is expected
shortly.
In other positive infrastructure news, India’s Rural Elecrification
Corporation, a leading state-run infrastructure finance company is
looking to raise INR350b–INR370b (US$5.4 billion–US$5.7 billion) in the
year to March 2014 to finance and prmote power
geneteration, transmission and distribution. Late September also saw the
announcement that the Asian Development Bank will lend US$500 million
to Rajasthan to set up a transmission network to support clean energy
projects in the state.
http://www.renewableenergyworld.com/rea/news/article/2013/12/renewable-year-end-roundup
No comments:
Post a Comment