The dust has settled. After a crazy whirlwind of activities, all
project documentation has been signed just minutes before midnight. The
solar project has been built despite all the roadblocks along the way.
It is now operational and connected to the grid, just before any imposed
deadlines. The press release has been issued. The sun is shining and PV
plant is producing as planned and everything is fine. Time to relax and
collect the cash flows for the next 20 or 25 years?
Dealing with the Dropbox Document Jungle
No time to relax for the developers, lawyers, investment officers,
tax advisors and investment bankers. They have long moved on to the next
shiny project and are out of the picture. New teams have taken over. They have been given access to a document
jungle in a Dropbox file and to a dozen of PV monitoring platforms. They
are starting to receive emails and calls from a myriad of solar service
partners and PPA off-takers. And stakeholders start screaming that
they want all sorts of reports. Time to relax?
This is part 1 in a series called “The life of a solar project after
the dust has settled”. Let’s get started dealing with the Dropbox
document jungle. We always like to ask solar investors and solar asset managers what
tool they use to manage their project documentation. We receive answers
all along the spectrum from physical document files, storage in a file
folder architecture, storage on a local network, to cloud based storage
in Dropbox, Sharepoint or storage on an online due diligence platform.
Or a combination of some of the above. About 70 percent of the time
Dropbox is included in the tools mentioned. And respondents start to
giggle because they believe this is not professional.
But it is not Dropbox as a document storage tool that makes an
organisation professional or not. The real questions you need to ask are
very often perceived as difficult ones. We have listed the 10 questions
we believe a professional solar owner/operator should ask itself:
- Are you sure you have ALL important project documentation?
- Are the contracts fully executed by all contract parties?
- Are you able to find important contracts within seconds?
- Did somebody in the team read these contracts?
- Has the person who read the contracts really understood everything (“lawyerese” can sometimes be hard to understand)
- Has the person identified inconsistencies between documents, or things that just do not make sense and need to be amended?
- Has the most important information in the contract been extracted?
- Does this information live in somebody’s head or is it accessible to team members?
- Is the extracted pricing/cost information consistent with the financial models?
- Did anybody else in the team audit the extracted information?
Did you not get further than question 1? It is frightening for the
solar industry, but you are actually in good company. About 80% of our
respondents are not even sure they have everything they need. As the
industry matures, this will undoubtedly need to change quickly. No time
to relax, time to get started.
Dealing with the Monster Consolidating Excel Spreadsheet
An important task of the solar asset manager is to monitor the
overall performance of the PV generating asset. Often they have
outsourced the live performance monitoring to a third party O&M
provider. This O&M provider will typically send the PV asset manager
monthly or weekly performance reports.
But PV asset managers increasingly want timely access to the
performance data of their portfolio. And they want it at their
fingertips. Sometimes they are frustrated with the time lag between
actual generation and the outsourced reporting. But mostly they need
timely data to produce their own internal management and financial
reports.
In an ideal scenario, all PV installations in the PV asset manager’s
portfolio are managed by the same PV monitoring system or by the same
O&M service provider. PV portfolio owner/operators often start out
with the best intentions to have performance measurement standardization
of their asset portfolio. But unless they control the entire value
chain from development, to construction to ownership, this will be
difficult to maintain: if a project or portfolio is offered to PV
investors at an attractive rate of return, those standardization
priorities often become secondary.
The PV asset manager will now need to log into the web portals of
multiple PV monitoring systems to retrieve performance data. The
complexity not only lies in maintaining different user names and
passwords, but also in maintaining consistency with the definition of
the performance parameters used by the different monitoring systems.
Particularly with performance measurements for performance ratio and
availability, they will observe a variety of definitions across
different PV monitoring systems. So what do PV asset managers do today to get timely access to consistent data across their entire portfolio?
Phase 1: Typically PV asset managers will initially
choose the path of “lowest resistance:" This path that does not require
any additional financial budget or senior management approvals. It will
require an analyst to create a consolidating spreadsheet. The analyst
will log into the different systems on a daily or weekly basis and
download the raw data. Fresh out of business school, the analyst will
load the spreadsheet with fancy macros to make adjustments to the data,
the formatting and so on. The spreadsheet will grow every day.
Everybody is happy because the problem is solved. But either one of
these scenarios happen. The spreadsheet has grown so big that one day it
does not open any more. Or somehow it got corrupted and nobody knows
exactly what happened to it, but the data can no longer be trusted. Or
the analyst leaves the company and nobody quite understands the macros.
Phase 2: Invariably follows Phase 1. It often needs a
crisis to obtain a financial budget. Some owner/operators will invest
in creating their own database. The advantage is that they can set it up
exactly as they want. But they need to have the necessary skill set
in-house to deal with the various performance indicator definitions. And
they will need to have skilled staff to maintain the database in the
long run. An alternative way achieving automation is to work with an
established PV monitoring aggregator, a company that has experience in
dealing with data from other monitoring companies.
Whatever the choices are that PV asset managers make, they will need
to bear in mind the main purpose of the consolidated data. They will
need to ask themselves the question: “Do I need the data for live
performance monitoring, for stakeholder reporting or for invoicing or
for all of the above?” There is little point in aggregating 5-minute
data, if the live performance monitoring is outsourced to an O&M
service provider. In such a case daily data is probably sufficient for
daily performance management and reporting. It is going to be interesting to see which choices the solar asset
management industry will adopt. But one thing is already clear: The days
of the monster consolidating Excel spreadsheet are numbered.