New Hampshire, USA --
Offshore wind development is being pushed further out into deeper
waters, emphasizing longer, higher-capacity transmission systems. Most
newer offshore wind farms from Europe to the U.S. are looking at
hundreds of kilometers of transmission lines: the U.K.
Crown Estate's
Round 3 allocations, interconnection systems from Germany's North Sea to
the U.K.'s National Grid Western Link, and the proposed Atlantic Wind
Connector in the U.S. Mid-Atlantic. Those distances are one of a number of factors driving a switch
from tried-and-true high-voltage AC (HVAC) to high-voltage DC (HVDC) for proposed offshore grids and as a suitable interface with different grids,
including meshing with AC back onshore. (Also in HVDC's favor: superior
voltage quality, fewer transmission losses, and better power flow
control.)
There's some debate whether HVAC technology can be improved and be
viable in performance and costs even when stretched out to 60-100 km
distances, but beyond 100 km or so where offshore wind farms are going
"there is no question DC is the only option," explains Joel Whitman,
principal at Whitman Consulting Group, who led a transmission-themed
panel at an offshore power conference
last week in Boston. Put some more numbers in HVDC's column: Navigant
Consulting expert Kris Torvik projects 30 GW of offshore wind will be
connected by HVDC by 2020, which will help to triple the market for high-voltage submarine power cables.
There are some significant hurdles to moving the offshore wind
industry from incumbent HVAC to HVDC. Roughly 9,000 km of offshore cable
will be installed over the next 15 years, noted Pierre Bernard,
formerly with European grid operator Elia Group, speaking on the
offshore wind event panel. (The U.K.'s Crown Estate has arrived at
roughly the same estimate.) One does not simply
order and install new high-voltage offshore cabling, however: very few
ships can handle the sheer amounts necessary for increasingly large
offshore wind farms, few ports can accommodate them, and an experienced
crew is scarce. As a result there's a massive backlog for the few firms
who have the resources; Torvik points to a $1-$2 billion backlog in HV
cable orders at Prysmian, ABB, and Nexans. Whitman estimates that
roughly 80 percent of insurable losses to date in offshore wind have
been cable-related, so this one area is arugably offshore wind
development's most impactful area to focus on reliability and costs.
Efforts are well in progress to make HVDC less costly in any number of ways.
Switching to DC can remove the need for offshore transformers and
platforms, and fewer components in the main power system translates to
better reliability and efficiency. To that end, GE Power Conversion
(formerly known as Converteam, acquired in 2011 and a former unit of Alstom) is touting what it says is a way to dramatically lower costs of offshore wind:
swap out the conventional wind turbine transformer with something it
calls PassiveBoost. It is essentially a medium-frequency transformer
with a diode bridge that converts the 33 kVAC waveform from the turbine
power converters into a 50 kVDC one, thus increasing the site's output.
Full-scale demonstration trials in the U.K. proved the system's
predicted efficiency and footprint (the same size, footprint and weight
as the existing turbine generator), according to GE.
Making a direct connection to a HVDC power grid reduces cable cost
and eliminates the need for an expensive and complex DC breaker,
according to the company. Which leads to the company's bigger claims
about the technology: it can lower levelized cost of energy for offshore
wind by 11-15 percent. As an apparent thumbs-up from the industry, GE
claims Seoniad Vass, director of renewable energy and low-carbon
technologies at Scottish Enterprise, was said to be "involved in the
early stages of the project."
http://www.renewableenergyworld.com/rea/news/article/2014/03/dc-transmission-tweak-promises-big-cost-benefits-for-offshore-wind
No comments:
Post a Comment