The early days of yet another prolonged cold weather snap are causing
concerns for grid operators along the East Coast. Daily spot market
prices are well above average, but that has not sufficiently dampened
demand.
Yet again this month, demand response resources have been
dispatched. In the PJM power pool that stretches from Chicago to the
mid-Atlantic, 150 MW of emergency demand response was called the night of the 22nd. That number was increased to 500 MW on the 23rd, and it was called upon again this morning, according to RTO Insider, a publication that monitors PJM.
RTO Insider noted that since Tuesday, PJM has issued numerous Post Contingency Local LOCM +0.62%
Load Relief Warnings characterized as “advance notice to a transmission
owner of the potential for manual load dump in their area.”
PJM, in a January 23 press release
calling on customers in the Baltimore and D.C. area to voluntarily
reduce consumption, noted that “The prolonged cold requires some
generating units to operate more often and for more hours than normal.
It also stresses generator components. Any resulting unplanned shutdowns
can further tighten power supplies.”
PJM Seek To Temporarily Lift Price Caps
The regional transmission operator is also seeking temporary relief from the Federal Energy Regulatory Commission (FERC) to temporarily lift the $1,000 price cap it can pay generators through March 1st.
PJM is doing so because available power plants must in fact generate
power and submit an offer of no more than $1,000 per megawatt-hour (MWh)
into the grid.
However, with natural gas costs so high (a large portion of the
generating fleet runs on natural gas), some generators’ operating costs
are north of the price cap. Generation costs are high as a consequence
of extraordinarily high gas prices. Normally in the $3.50 to $4.50/mmBtu
range long-term, spot market gas prices this week have
reached$140/mmBtu.
PJM’s request to the FERC will seek a retroactive waiver to apply to
all resources dispatched this week, and make them whole for documented
generation costs. It will not apply to operations during the first week
of January. Going forward, PJM is requesting relief from the price cap
to allow generators to bid in and set the Locational Marginal clearing
price (though the price paid to demand response resources will remain
limited to $1800/MWh). PJM said in a notice to its members that “PJM has
consulted with counsel and believes the anticipated retroactive request
will likely be accepted by the FERC.”
NYISO Following Suit
Further to the north, the New York ISO is seeking a similar FERC
approval to lift its $1,000/MWh cap and compensate plants that can show
their variable costs exceeded that limit, according to Energy Choice Matters. Unlike PJM, the NYISO is not seeking authority for generators to set either Day-Ahead or Real-Time spot-market prices.
NYISO stated that the waivers were “necessary to ensure the reliable
operation of the New York State Power System” and noted that “weather
and unprecedented natural gas market conditions have driven certain
gas-fired generators’ fuel costs to previously unseen levels.”
The ISO recognizes that an increase in sport market prices will
“increase the costs ultimately paid by Loads. However, such increased
costs should not be viewed as ‘harming’ Loads because they are necessary
to ensure continued, reliable electric service during extreme weather
conditions.”
What About Customers?
Energy Choice Matters takes issue with this waiver request, noting that
“Customers are absolutely harmed by the increased compensation
granted to generators. It changes a fundamental benefit of the bargain
forced on customers, who are compelled to forward procure capacity to
ensure “reliability.”
The publication further comments that the capacity payments made to
generators was done so with the understanding that the capacity was to
be available whenever necessary:
All of the capacity suppliers in New York are aware of the long-standing $1,000/MWh bid cap. Capacity suppliers who bid for the right to supply NYISO with capacity, and who cleared the market, took on the obligation of serving this future need knowing full well what existing market rules were.”
The generators also knew what market risks were as well, a risk they
voluntarily took on, and could have hedged for on the gas supply side.
Energy Choice Matters comments “In fact, to grant the NYISO’s
requested waivers would create a moral hazard freeing generation owners
from undertaking any prudent management of their business. No longer
would generators have to engage in practical management to limit their
variable costs; so long as the power is needed to maintain ‘reliable
operations’ of the grid.”
The longer this cold snap lasts, the more money will be at stake.
Either generators or consumers will lose. The money comes from one
pocket or the other. Despite frigid temps, expect the argument to heat
up considerably on this one in the days to come.
http://www.forbes.com/sites/peterdetwiler/2014/01/24/cold-weather-and-price-volatility-in-northeastern-power-markets-generators-seek-relief/?ss=businessenergy
No comments:
Post a Comment